December 27, 2020 at 1:35 pm
#38254
Cesar Otero Lucas
Participant
Dear all,
For me the three main reasons:
1.- Over estimating the final result focusing only in the best case
2.- Poor due dilligence
3.- In DD process, not analyzing the technical issues of the plants and equipments you are acquiring. In my experience this factor is a key factor.
Regards,
César Otero